Installation

Installation phase

The installation can roughly be divided into the following five areas:

  • Basework/Earthwork
  • Drainage
  • Sub-base (Elasticlayer, asphalt, underground heating, surface irrigation)
  • Synthetic surfacing
  • Installation of sport equipment (goals, bench)

A quality basework including the drainage and sub-base work is necessary for the longevity of a turf installation. A solid basework guarantees that the underground does not become uneven after a short time which consequently also affects the evenness of the final football turf installation.

When laying the synthetic grass, the installer should make sure that the cuts are straight and the seams are clued properly. Should a defect be spotted after a certain time of use, the installer should be contacted directly and then do the necessary repair work. This should be clearly defined in your warranty.